Telangana HC seeks Damagundam afforestation timeline, questions sapling survival
HYDERABAD: The Telangana High Court on Monday directed the state government to complete compensatory afforestation within a fixed timeframe. The plantation drive aims to make up for forest loss during the construction of an Indian Navy radar project at Damagundam in Vikarabad district, as reported by TOI.
A bench headed by acting Chief Justice P Sam Koshy and Justice Suddala Chalapathi Rao also sought details of sapling survival. It asked whether at least 75% of the planted saplings had survived.
The court said the government must replace withered saplings and meet the afforestation target. It also directed the state to file an additional affidavit on plantation and restoration work.
HC questions survival rate of saplings at Damagundam
The bench issued the directions while hearing a public interest litigation (PIL) against the allocation of land for the radar project. The petition also alleged large-scale damage to flora and fauna around the project site.
The court adjourned the matter to November 17 for further hearing.
Earlier, the High Court had directed the government to replace withered saplings. It had also asked the state to carry out the proposed afforestation under its target plan between May and December 2026.
Govt reports 70-80% sapling survival rate
Government counsel told the court that forest department officials had inspected the site. The inspection assessed the progress of the afforestation work.
According to their report, some saplings were planted two years ago and others a year ago. The estimated survival rate ranged from 70% to 80%.
The government also informed the bench that it had deposited the amount indicated by the forest department. The funds were meant for compensatory afforestation in lieu of the forest land.
HC seeks timeline for pending plantation work
Government counsel said the process would take around two years. Plantation, restoration of damaged tree cover and related work were under way.
However, the bench questioned the survival figures. It asked what had happened to the remaining 25% to 30% of saplings.
The court directed the government to specify the work pending in the remaining areas. It also sought a clear timeline for completing the plantation and restoration activities.