HYDERABAD: The District Consumer Disputes Redressal Commission-III, Hyderabad, has directed Fortune 99 Homes and its partners to execute and register a sale deed for a 294-square-yard residential plot in favour of a customer. It also ordered them to pay ₹1 lakh as compensation and ₹10,000 towards complaint costs.
In its September 29, 2026, order in Consumer Case No. 337 of 2025, the commission found deficiency in service and unfair trade practice. The company had failed to execute the sale deed despite receiving the agreed amount and an additional ₹3.5 lakh.
The bench comprised president M Ramgopal Reddy and members J Shyamala and D Sreedevi. The opposite parties did not appear or contest the complaint despite receiving notice.
Customer paid ₹25.9 lakh for plot in Mucherla
According to the complaint, Bolla Ravinder Reddy agreed to buy a 259-square-yard open plot in NCS Fortune Medi City at Mucherla village in Kandukur mandal, Rangareddy district, in 2021. The agreed rate was ₹10,000 per square yard, taking the total price to ₹25.9 lakh.
The complainant said he paid the amount through cheques and cash between March and August 2021. On April 16, 2021, Madhirala Rosi Reddy signed an agreement of sale on behalf of Fortune 99 Homes. The agreement allotted plot No. A-145 to the customer.
Company representatives assured him that they would register the sale deed after the Hyderabad Metropolitan Development Authority (HMDA) approved the layout. However, the company failed to complete the registration for an extended period.
Company allegedly demanded another ₹3.5 lakh
The complaint stated that the company informed the customer in 2023-24 about changes to the layout following approval. These changes affected plot numbers and sizes. The company subsequently linked the original plot to a revised plot identified as No. 338, North Part.
The complainant alleged that the company demanded an additional ₹3.5 lakh for the difference in plot area, approval-related charges and registration processing. He said he paid the amount in cash to an employee identified as Devilal in January 2024.
According to the complaint, the employee acknowledged the payment through WhatsApp messages, but the company did not issue a receipt.
The complainant also said the company sent him a draft sale deed in January 2024. The document described the revised plot as measuring about 294 square yards. Despite this, the company did not execute or register the final sale deed.
Commission finds deficiency in service
The commission noted that the complainant submitted an evidence affidavit and supporting documents. The opposite parties remained absent despite receiving notice. As a result, they did not challenge the complainant’s evidence and allegations.
The commission held that the company’s failure to execute and register the sale deed amounted to deficiency in service under Section 2(11) and an unfair trade practice under Section 2(47) of the Consumer Protection Act, 2019.
It directed Fortune 99 Homes and its partners to execute and register the final sale deed for the revised HMDA-approved plot. The plot corresponds to the original plot No. A-145 and is now identified as plot No. 338, North Part, measuring 294 square yards.
The commission also directed the opposite parties to pay ₹1 lakh as compensation and ₹10,000 towards complaint costs.